The following is the Operation Torch Bearer schedule.
| Thursday 9 November 2000 |
| |
| 1800 |
CST |
Set up at Elkhorn Armory |
| 2200 |
CST |
End operations for the day |
| |
| Friday 10 November 2000 |
| |
| 0900 |
CST |
Test computer & comm equipment at Armory |
| 1900 |
CST |
Install/test computer & comm eqpt at C59 |
| 2200 |
CST |
AAR for set up and functional testing phase |
| 2230 |
CST |
End operations for the day |
| |
| Saturday 11 November 2000 |
| |
| 0700 |
CST |
Billeting area clean up |
| 0730 |
CST |
Mission registration begins |
| 0800 |
CST |
Opening briefing |
| 0830 |
CST |
Training and testing begins |
| 1200 |
CST |
Lunch and AAR for morning tng session |
| 1300 |
CST |
Afternoon tng begins, testing continues |
| 1630 |
CST |
AAR for afternoon training session |
| 1700 |
CST |
Testing ends for the day |
| 1705 |
CST |
Catholic Mass (transportation provided) |
| 1830 |
CST |
Dinner break |
| 1930 |
CST |
Evening training begins |
| 2130 |
CST |
AAR for evening training session |
| 2200 |
CST |
End of operations for the day |
| |
| Sunday 12 November 2000 |
| |
| 0700 |
CST |
Billeting area clean up |
| 0730 |
CST |
Mission registration begins |
| 0800 |
CST |
Opening briefing |
| 0830 |
CST |
Training and testing begins |
| 1200 |
CST |
Lunch and AAR for morning tng session |
| 1300 |
CST |
Afternoon tng begins, testing continues |
| 1530 |
CST |
Exercise AAR, testing ends |
| 1630 |
CST |
Mission tear down begins |
| 2100 |
CST |
End of operations for the day |
| |
| Monday 13 November 2000 |
| |
| 1000 |
CST |
Continue tear down operations |
| 1700 |
CST |
AAR for tear down phase |
| 1800 |
CST |
End of Operation Torch Bearer |
| |
 |
| |